Every once and a while I come across language in a contract that makes be ask that exact question. The language in question was in a contract involved with a lawsuit between The London Fire and Emergency Planning Authority v Halcrow Gilbert Associates and Others.
The specific limitation of liability read as follows:
“Neither the contractor nor the purchaser shall be liable to the other by way of indemnity or by reason of any breach of the contract or of statutory duty, or by reason of tort (including but not limited to negligence) for any loss of profit, loss of use, loss of production, loss of contracts or for any financial or economic loss or for any indirect or consequential damage whatsoever that may be suffered by the other.”
The first thing I always recommend when you have a commitment that runs on like this is to split it down to what each of the individual commitments are to make sure that you understand it and each works for you. In this paragraph the language disclaimed liability for both parties for six different things. Let’s take a look at each of these to see the real impact of the language;
1.“Neither the contractor nor the purchaser shall be liable to the other by way of indemnity. This means that even if there was an indemnity provision in the agreement the party providing the indemnity was not liable under the indemnity making it useless.
2. "Neither the contractor nor the purchaser shall be liable to the other by reason of any breach of the contract or of statutory duty”. This eliminates the potential for either party to be liable under contract law for either breach or failing to meet a statutory duty.
3. “Neither the contractor nor the purchaser shall be liable to the other by reason of tort (including but not limited to negligence” This eliminates either party being able to claim not just under contract, but also by tort for injuries or damage sustained by a tortuous act.
4. “Neither the contractor nor the purchaser shall be liable to the other for any loss of profit, loss of use, loss of production, loss of contracts”
This excluded claims for loss of profits, use, production or contracts
5.“Neither the contractor nor the purchaser shall be liable to the other for any financial or economic loss”. This eliminated the right to claim for any financial or contractual loss.
6.“Neither the contractor nor the purchaser shall be liable to the other for any indirect or consequential damage whatsoever that may be suffered by the other.” This excludes any indirect or consequential damages.
The net effect of all of these exclusions was that neither party would be liable to the other party for anything. It eliminated all potential claims for damages. It eliminated all remedies available under contract or tort. The only potential claim that could still be made would be under equity. The two primary remedies under equity are specific performance and injunctive relief. In a contract situation unless what you offer is so unique to you that only you could provide it, courts won’t order specific performance. Injunctive relief is used to stop people from doing things and I don’t think you can stop someone from not working or not performing as that would be equivalent to ordering performance.
In the end the court will try to enforce the intent of the parties to the contract and here, with respect to liability the intent was clear that neither party would be liable to the other party for anything. While one party such as a buyer may want to be absolved of liability for everything except payment, this was the first time I ever saw a clause that completely excused both parties of any liability whatsoever.
What were they thinking?
The fastest and easiest way to find topics on my blog is via my website knowledgetonegotiate.com The "Blog Hot Links" page lists all blogs by subject alphabetically and is hyperlinked to the blog post. My book Negotiating Procurement Contracts - The Knowledge to Negotiate is available at Amazon.com (US), Amazon UK, and Amazon Europe.
Tuesday, May 29, 2012
Business Interruption Insurance
Business Interruption Insurance (also known as business income coverage) is a policy that may be purchased where in the event of a catastrophe, such as a fire, tornado, explosion, or other disastrous event causes your place of business to be temporarily unusable, forces you to relocate, or close down your business for a period, the policy would pay for:
1.Profits that you would have earned had you property not been damaged. This would normally be calculated based upon your past financial records of earnings.
2.Operating expenses that will still occur at the location. For example you could still have taxes, insurances, security and other expenses at the site even though you are not able to use the site.
They will normally not include labor or management costs as those costs are usually covered by unemployment benefits. Business interruption insurance may include as a separate item “extra expenses”. Extra expenses would be additional expenses that you incur that help decrease the cost of the business interruption. For example extra expense insurance could cover incremental expenses required to operate out of a temporary location if that would decrease the cost of the business interruption.
While this is not an insurance that you would require the to Supplier maintain under a contract, it’s an important concept for negotiators to understand especially when negotiating force majeure provisions.
For example: Assume that you had a contract to purchase 100,000 units of a product over a year and the supplier had a disaster such as a fire after only delivering 10,000 units. It was the only location where they produced the item. They cannot produce it in another location as the capital equipment required to produce it was destroyed in the fire. It will take them a year to recover. In a normal force majeure clause the party that suffered the force majeure event is excused from performance during the period of the force majeure. The party that did not suffer the force majeure is not excused. This means that a year from now the buyer would still have the obligation to purchase the remaining 90,000 units. You may not want that obligation and as part of the negotiation of the force majeure clause you include language that if there is a force majeure and the supplier is unable to recover within one hundred and twenty (120) calendar days, you have no obligation to purchase the remaining volume.
The Supplier seeing the potential loss of revenue and profit is opposed to agreeing to this. You then ask the supplier whether they have business interruption insurance. If they do, it becomes a simpler argument. If the insurance is already paying them for the lost profit they didn’t make for not performing, and insurance is paying them for the losses they sustained to the equipment or materials on hand that were damaged, haven’t they already been compensated? They have been made whole.
Forcing you to purchase it a year from now may:
1. Be selling you a product that you no longer need.
2. Be requiring you to shut off an alternative source of supply that helped you and that you had to invest in to not be impacted by their force majeure
3.Be selling you something that is no longer state of the art.
Any investments they made to produce the product for you will either have been paid for out of the insurance proceeds for the lost equipment or would have been paid for out of the profit they were paid by the business interruption insurance. I would then remind them that force majeure is about providing excusable delays when there are disasters. They are not there to guarantee future revenue and profits.
1.Profits that you would have earned had you property not been damaged. This would normally be calculated based upon your past financial records of earnings.
2.Operating expenses that will still occur at the location. For example you could still have taxes, insurances, security and other expenses at the site even though you are not able to use the site.
They will normally not include labor or management costs as those costs are usually covered by unemployment benefits. Business interruption insurance may include as a separate item “extra expenses”. Extra expenses would be additional expenses that you incur that help decrease the cost of the business interruption. For example extra expense insurance could cover incremental expenses required to operate out of a temporary location if that would decrease the cost of the business interruption.
While this is not an insurance that you would require the to Supplier maintain under a contract, it’s an important concept for negotiators to understand especially when negotiating force majeure provisions.
For example: Assume that you had a contract to purchase 100,000 units of a product over a year and the supplier had a disaster such as a fire after only delivering 10,000 units. It was the only location where they produced the item. They cannot produce it in another location as the capital equipment required to produce it was destroyed in the fire. It will take them a year to recover. In a normal force majeure clause the party that suffered the force majeure event is excused from performance during the period of the force majeure. The party that did not suffer the force majeure is not excused. This means that a year from now the buyer would still have the obligation to purchase the remaining 90,000 units. You may not want that obligation and as part of the negotiation of the force majeure clause you include language that if there is a force majeure and the supplier is unable to recover within one hundred and twenty (120) calendar days, you have no obligation to purchase the remaining volume.
The Supplier seeing the potential loss of revenue and profit is opposed to agreeing to this. You then ask the supplier whether they have business interruption insurance. If they do, it becomes a simpler argument. If the insurance is already paying them for the lost profit they didn’t make for not performing, and insurance is paying them for the losses they sustained to the equipment or materials on hand that were damaged, haven’t they already been compensated? They have been made whole.
Forcing you to purchase it a year from now may:
1. Be selling you a product that you no longer need.
2. Be requiring you to shut off an alternative source of supply that helped you and that you had to invest in to not be impacted by their force majeure
3.Be selling you something that is no longer state of the art.
Any investments they made to produce the product for you will either have been paid for out of the insurance proceeds for the lost equipment or would have been paid for out of the profit they were paid by the business interruption insurance. I would then remind them that force majeure is about providing excusable delays when there are disasters. They are not there to guarantee future revenue and profits.
Subscribe to:
Posts (Atom)